In-Depth Analysis Of Solar Project Completion Timelines Released By NREL

2017-09-11 09:52:28 Prostar Solar Energy Read

NREL interconnectionData from more than 30,000 solar photovoltaic (PV) installations throughout the United States has been compiled and analyzed by the Energy Department’s National Renewable Energy Laboratory (NREL) as part of a new study to explore the relationship between interconnection regulations and actual project completion timelines.

The quick takeaway here? Interconnection process delays are fairly common — and generally range from simple of a couple of days up to several months. The study authors note that the streamlining of the application review + final authorization processes could benefit utilities as well as solar consumers, by reducing the notable time and costs currently accompanying the process of adopting solar energy.

We now have a clearer understanding of the different process elements associated with connecting a PV system to the grid, such as how long it takes to review and approve an application for interconnection, how long it takes to construct and inspect a system, and how long it takes to get final authorization from the utility,” stated lead author Kristen Ardani, a solar technology markets and policy analyst at NREL. “This report represents the first data-driven evaluation of how PV deployment time frames compare to state regulations in key solar markets.”

A recent press report sums up some of the key points:

 